Public Works Secretary Giovanni Lopez ordered the contractor of the Gandara Parallel Bridge Project to strictly meet its April 2027 completion deadline following a structural collapse in Gandara, Samar.
The incident occurred at 7:30 a.m. on November 17, 2026. Two prestressed concrete Type V girders fell during installation along the Gandara diversion road.
No workers or bystanders were injured in the accident.
Initial technical assessments ordered by the Department of Public Works and Highways indicated that the girder failure was not caused by substandard construction materials. The bridge piers and abutments remained stable.
Investigators pointed to a procedural lapse on the site.
According to project contractor B. Vicencio Builders Inc. (BVBI), two girders measuring 35 meters long were brought to the site on the evening of November 16.
One end of a partially installed girder rested on an elastomeric bearing pad. The opposite end was temporarily supported by a roller.
Project engineers instructed workers not to alter the temporary arrangement without authorization. Two workers removed the roller early the following morning.
The partly placed girder dropped its bracing and collapsed. It hit the adjacent beam and caused ruin to both components.
Dropping from six meters up onto irregular terrain, the pair of 35-meter beams shattered upon impact.

The Gandara II Parallel Bridge Project is structured in two phases with a combined cost exceeding P242 million. That corrected earlier estimates that placed the figure at P512 million.
The first phase involves a 70-linear-meter bridge with a project cost of PHP92.61 million.
The company will solely shoulder the cost of the materials and labor services for their replacements. We will forthwith do so by working energetically and prudently to avoid any unnecessary delay in the project.
B. Vicencio Builders Inc., Contractor
The successful placement of those beams would have represented 68 percent of the project’s completion, the contractor said.
President Ferdinand Marcos Jr. issued a directive to secure public safety and prevent further delays. Lopez inspected the site on November 20.
The public works chief warned the contractor that the government would not tolerate a repeat of the incident. Severe consequences would apply if something similar happens again, Lopez said.
The contractor has committed to maintaining the original timeline, which is 2027. We will not change that. If they need to work 24 hours a day, seven days a week, then they should do so.
Giovanni Lopez, Public Works Secretary
Regional Director Edgar Tabacon reported that DPWH Eastern Visayas personnel initiated clearing operations and removed debris. Installation work for additional replacement girders got underway.
The older span was closed to traffic in October 2020. An overloaded truck exceeding its 18-ton limit crossed it and sustained serious structural damage.
The closure forced motorists to rely on alternative routes for more than six years. That created long-standing transportation difficulties in the municipality.
Giovanni Lopez, a native of Tuguegarao, Cagayan, is a lawyer and certified public accountant who founded a law firm in Manila in 2007. He spent five years at the Department of Transportation, rising from Legal Service Director to Undersecretary for Administration, Finance, and Procurement, and served as Chief of Staff to then-Secretary Arthur Tugade.
In September 2025 he became Acting Secretary of Transportation, issuing a memorandum requiring senior officials to commute by public transit weekly. President Marcos appointed him Secretary of Public Works and Highways on October 26, 2026, swapping roles with Vince Dizon to accelerate reforms in both agencies.
Construction on the replacement project began on December 17, 2024. Completion is targeted for April 2027.